A paver patio needs three things in the right amounts: the pavers, a compacted gravel base, and a thin layer of bedding sand. Measure the patio once, and you can work out all three before you go to the supplier.

What goes under a paver patio

From the bottom up:

  1. Compacted gravel base. Unilock's installation guide gives a typical base of 6 to 8 inches for patios and walkways, and 10 to 14 inches for driveways, using 3/4-inch crushed gravel compacted in layers 2 to 3 inches thick (Unilock basic tech guide).
  2. Bedding layer. The same guide lays pavers on "a 1" thick bed of coarse sand", or on 1/8-inch open-graded chip.
  3. Pavers, held in place by edge restraints spiked into the base.

The base does the structural work. Skimping on it is the most common reason patios sink or heave.

Step 1: Measure the area

Measure length and width in feet. For an L-shape, split it into rectangles and add them up; for a curve, measure the rectangle around it and treat the extra as cuts. The square footage calculator helps with odd shapes.

The examples below use a 12 × 12 ft patio (144 square feet).

Step 2: Count the pavers

Pavers are sold by the piece or by the square foot. The number depends on the paver size and the joint between them.

With common 8 × 4 inch pavers and a 1/8-inch joint, the 12 × 12 ft patio covers 144 square feet and needs 619 pavers.

With 12 × 12 inch pavers, the same patio needs 142.

Buy extra for cuts along the edges and around curves, and a few spares for future repairs. Ask your supplier how much extra they recommend for your pattern: herringbone and curved edges waste more than a straight running bond. The pavers calculator works this out for any size and joint.

Step 3: Work out the gravel base

The base is a volume: length × width × depth. Gravel is usually sold by the cubic yard (bulk) or by the bag.

For a 6-inch base under the 12 × 12 ft patio, with 10% extra for compaction and uneven ground, order about 2.933 cubic yards (79.2 cubic feet).

At 8 inches, it's 3.911 cubic yards. On soft or clay soil, or where water collects, use the deeper end of the range.

Loose gravel shrinks when it's compacted, which is why the extra matters. Your supplier can tell you how much their material compacts and how much a cubic yard weighs. The gravel calculator also gives cubic meters, and the gravel guide covers ordering in more detail.

Step 4: Work out the bedding sand

A 1-inch sand layer is the same volume formula with a depth of 1 inch. For the 12 × 12 ft patio with 10% extra, that's 0.4889 cubic yards, or 13.2 cubic feet. Sand bags are usually labeled by weight, so check the bag for the cubic feet it covers before working out how many to buy.

Step 5: Edging and joint sand

  • Edge restraint: measure the outside edge that isn't against a wall or the house. A 12 × 12 ft patio against the house has 36 feet of open edge. The linear feet calculator adds up runs of different lengths.
  • Joint sand: after the pavers are down, sand (often polymeric) is swept into the joints. Coverage depends on the paver size and joint width, so follow the bag's coverage chart.

Your shopping list

For the 12 × 12 ft patio with 8 × 4 inch pavers and a 6-inch base:

Material Amount
Pavers (8 × 4 in) 619, plus extra for cuts
3/4-inch crushed gravel, 6-inch base about 2.933 cubic yards
Coarse bedding sand, 1 inch about 13.2 cubic feet
Edge restraint the open edge, e.g. 36 ft
Joint sand per the bag's coverage chart

Tips before you dig

  • Slope it for drainage. Unilock's guide says every installation should be "sloped away from the house/building for proper drainage". Plan the slope before you dig so the base follows it.
  • Call before you dig. In the US, call 811 a few days ahead to have underground utility lines marked. It's free.
  • Rent a plate compactor. Compacting the base in thin layers is what keeps pavers level for years.
  • Building a step or a raised patio? A raised edge needs a wall. The retaining wall calculator counts the blocks.

Measure your own patio and run the numbers through the pavers and gravel calculators, then take the list to your supplier and ask them to check it against the products they stock.

Updated

  • How to calculate gravel

    Work out how much gravel to order from length, width and depth, with the formula, worked examples and how much extra to buy.

  • How to calculate concrete

    Estimate concrete volume and the number of 60 lb or 80 lb bags for slabs and footings, including a waste factor.

  • How to calculate paint

    Estimate paint for a room from its size, the number of coats and the coverage on the can.

  • How to calculate rafter length

    Run, rise and pitch to rafter length with the ridge board and overhang, worked for 6/12 and 12/12 roofs, and the board length to buy.

  • How much siding do I need?

    Work out siding squares from wall length and height, gables and openings, with waste and a cost estimate.

All guides by topic